PM Surya Ghar: subsidy steps for homeowners

Portal registration, DISCOM approval, commissioning and when the central subsidy actually reaches your bank account.

15 July 2026 · 7 min read · Prepared by SRG from Wavesun Energy published guidance.

PM Surya Ghar: subsidy steps for homeowners
Key takeaways
  • Central financial assistance is 60% of benchmark cost for the first 2 kW and 40% for the additional 1 kW, capped at ₹78,000 for systems of 3 kW and above. Up to 1 kW it is ₹30,000 and at 2 kW it is ₹60,000.
  • Consumer registration on the National Portal with mobile number, Aadhaar and electricity bill details. Vendor selection from empanelled vendors, followed by a site survey and technical proposal.
  • From application to commissioning the usual range is 60–120 days. Delhi NCR DISCOMs often complete in 60–90 days. Subsidy delays of 30–60 days after inspection are seen in some states.
  • SBI offers up to ₹6 lakh at about 8–9%; Canara Bank, PNB, Bank of Baroda and Indian Bank offer up to ₹5 lakh at roughly 8.5–9.5%, typically for up to 10 years. Use our EMI calculator to model the instalment against expected savings.

What the scheme pays

Central financial assistance is 60% of benchmark cost for the first 2 kW and 40% for the additional 1 kW, capped at ₹78,000 for systems of 3 kW and above. Up to 1 kW it is ₹30,000 and at 2 kW it is ₹60,000.

Eligibility is generally 1 kW to 10 kW per household, installed by an MNRE-empanelled vendor using ALMM-listed modules. Battery storage is not covered.

The seven steps, in order

Consumer registration on the National Portal with mobile number, Aadhaar and electricity bill details. Vendor selection from empanelled vendors, followed by a site survey and technical proposal.

Feasibility application to the DISCOM with a single-line diagram and structural assessment, then DISCOM approval — electrical feasibility, transformer capacity and sanctioned load — which typically takes 15–30 days.

Installation and commissioning with ALMM-listed modules and MNRE-empanelled inverters, then net-meter installation and physical inspection, and finally subsidy disbursement to your bank account, usually 15–30 days after inspection.

Timelines to plan around

From application to commissioning the usual range is 60–120 days. Delhi NCR DISCOMs often complete in 60–90 days. Subsidy delays of 30–60 days after inspection are seen in some states.

Bank finance while you wait

SBI offers up to ₹6 lakh at about 8–9%; Canara Bank, PNB, Bank of Baroda and Indian Bank offer up to ₹5 lakh at roughly 8.5–9.5%, typically for up to 10 years. Use our EMI calculator to model the instalment against expected savings.

Five mistakes that delay payment

Applying without confirming vendor empanelment; choosing non-ALMM modules; oversizing beyond sanctioned load; skipping DISCOM feasibility and installing early; and mismatched names on the portal, bank account and electricity bill.

What this means for your property

Every roof is different. Share your bill and district and we will size the system, confirm the subsidy tier and show the payback — free and without obligation.

Get my free assessment

Talk to someone who sizes systems all day.

Free survey, itemised quote, and an honest answer about whether solar is worth it on your roof.

Call WhatsApp Free quote